FOTO SEQUENCES REFERRED TO HOUSE CONSTRUCTION
|
1. 2 BRICK BUILT HOUSES OF 1 AND 2 PLANTS |
15.06.06
19.06.06
|
Beginning of the 2 houses is exactly the same: The terraplain and preparing of foundations (on the left, 15.06.06), on the right the slab construction (19.06.06), at the left for a 1 plant house, at the right for a 2 plants house
|
|
|
|
|
|
|
|
|
29.06.06
|
Both houses advanced one step, at the left the 1-P-House, at the right the 2-P-House: |
|
|
|
|
|
|
|
|
04.07.06 |
This is the roof construction (in Germany: Richtfest) of both houses |
|
|
|
|
|
|
|
|
18.07.06
|
The roof is nearly closed, windows are built in, both houses are closed only 5 weeks after having initiated construction. |
|
|
|
|
|
|
|
|
10.08.06
|
The interior building termination is going ahead rapidly. The dry walls are fixed, electrical installations and interior wall covering is completed. Heating and plumbing is advancing. |
|
|
|
|
|
|
|
|
15.08.06
|
Heating system and plumbing is concluded in the 1 plant house, also the rough floor construction. The 2 plant house will follow this week . |
|
|
|
|
|
|
|
|
29.08.06
|
Exterior wall covering is in execution at the 1 plant house. This will be executed in the 2 plant house during this week. Rough floor, plumbing and heating installations are concluded. |
|
|
|
|
|
|
|
|
10.09.06
|
Exterior wall covering is finished in the 1 plant house. The finish of exterior wall covering will be executed in the 2 plant house during this week. Drying period is going on now for 2 weeks more. Then the internal finishing will begin. |
|
|
|
|
|
|
|
|
19.09.06
|
The drying period of the 1 plant house has finished. Tyles and sanitary objects are being mounted. In the 2 plant house will be installed a complex solar and heat pump system. The drying period after beginning of working of the floor heating will be completed within 1 week. Then the internal finishing will begin here, too.
|
|
|
|
|
|
|
|
|
29.09.06
|
The 1 plant house is finished, only 3 month and some days after initiated construction. The technically complex 2 plant house is now completed outside. Internal finishing is in execution and will be terminated within aprox. 2 weeks.. |
|
|
|
|
|
|
|
|
16.10.06
|
|
|
|
Internal finishing of the 2 plant house is in course and close to be terminated. Next week, the hand over of this house is preset . |
|
|
|
|
|
01.11.06
|
|
|
|
Internal finishing of the complicated 2 plant house is executed, too. The house is handed over to the client after a 5 months construction time. |
|
|
|
|
|
2. NORTHAMERICAN HOUSE CONSTRUCTION - 2-PLANT OFH | |
15.12.2004
|
In Falkensee near Berlin a new Northamerican One Family House was constructed. At this point, the foundations are built and there were continous informations as to the construction efforts on this site. The wood works are now in execution. |
TIL 22.12.2004
|
|
12.01.2005
TIL 19.01.2005
|
|
15.03.2005 |
State - interior at least finished |
|
|
28.05.2005 |
The home is terminated |
|
|